Delhi metro driverless train rams into wall during trial run

Wed, 20 Dec 2017 00:45:47    PTI

New Delhi: A Delhi metro driver-less train crashed into a wall today at the Kalindi Kunj depot while on a trial run, six days before its inauguration by Prime Minister Narendra Modi, an official said.

The Delhi Metro Rail Corporation (DMRC) official said the metro train was on a trial run on the new magenta line that was to be opened by Modi on December 25.

The front portion of the metro train and a stretch of the depot's boundary wall was damaged, the official said.

There were no casualties, he added. 

Delhi Metro Rail Corporation DMRC has issued an incident report:

An incident occurred at 3.40 PM (1540hrs) at the Kalindi Kunj Metro depot today which is under commissioning. A trial train was moved from the workshop without testing the brake system as a result of which, while the train was moving up the ramp for washing, it rolled back and hit the adjacent boundary wall. No person was injured in the incident.

As per normal procedure prescribed, when a train enters the workshop, the brakes of the train are decommissioned so that the train and its systems including the brakes can be freely checked. As per procedure, once the train is again re-commissioned, the brakes should have been tested by the maintenance staff in the depot before the train left the shed. The train movement inside the workshop area is done manually and not by the signalling system.

Prima facie, it appears, this was not done and subsequently, the person who took charge of the train from the maintenance staff also did not check the brake and proceeded with the train up to the washing plant built on a ramp. While stopping at the ramp, since the brakes were not available, the train rolled back causing this incident.

MD, DMRC has ordered a high level enquiry into this incident by a committee of three officers of the rank of Executive Directors consisting of Executive Director/ Rolling Stock (Project), Executive Director/ Rolling Stock (O&M), Executive Director/ Operations. Prima facie it appears, to be a case of human error and negligence and appropriate action will be taken after the enquiry.